4. Case Study — Recovery

Fan #1 Failure: timed gate → P/T picks the true swap → verify → recover

Module activation for TCCS Auxiliary Fan #1 Failure under P/T recovery

Scenario 24 · knowledge graph + cardinality fixed · P/T recovery · 60 s timed gate · procedure execute · 3600 s run

+4 s · diagnosis

KG returns candidates (symptom overlap). Scores become Pi; catalog ETRs become Ti

+4 – 64 s · timed gate

Hold first pick for 60 s after first nonzero evaluation so early score mass can settle

+64 s · first pick

P/T ranks Fan #1 Failure first (P=0.37, T=20 min) — true fault, first try

+64 – 1264 s · execute

Auxiliary fan swap-out runs; experimenter accepts the required procedure

+1264 – 1324 s · verify / recover

1 min window: alarms drop → success (TTR ≈ 21 min from injection)